0451 117 275 michael@directdemolition.com.au

What's Included in a Sydney Demolition Quote

Demolition quotes vary wildly in what they actually include. Here's the line-item breakdown to look for so you can compare apples to apples.

Demolition quotes vary wildly in what they actually include. Here's the line-item breakdown to look for so you can compare apples to apples.

One demolition quote at $22,000 and another at $32,000 might be for completely different scopes. Here's exactly what a proper Sydney demolition quote should include — and what to ask if it doesn't.

The Standard Line Items

  • Mobilisation: machine and crew to site
  • Service disconnection coordination (you typically pay utilities direct)
  • Asbestos survey and removal (if applicable)
  • Mechanical demolition of the structure
  • Hand demolition where required (boundary walls, neighbouring structures)
  • Concrete slab and footing removal
  • Site clean-up and rake-over
  • Waste loading, transport and licensed tip disposal
  • Pool/spa demolition (if applicable)
  • Final clean and tip dockets

What Should Be in Writing

  • Fixed total price, not "estimate"
  • SWMS and demolition methodology
  • Asbestos plan if any asbestos is suspected
  • Inclusions and clear exclusions
  • Insurance details (Public Liability $20M is the Sydney market norm)
  • NSW Demolition Licence number
  • Validity period

Common Exclusions (Read the Fine Print)

  • Service disconnections (Sydney Water/Ausgrid/Jemena) — usually owner's cost direct to utility
  • Tree removal or arborist work
  • Certifier or DA fees
  • Imported clean fill if you want the site filled
  • Termite treatment
  • Rock breaking beyond a stated quantity

Hidden Costs to Watch For

  • "Plus tipping fees if exceeds X tonnes" — get an estimated total tonnage
  • "Plus asbestos at $X/m² if found" — push for survey first
  • "Stand-down rates" if site isn't ready — agree what counts as ready
  • Subcontractor markups — ask if any work is subcontracted

How to Compare Two Quotes Fairly

Put both quotes side-by-side line-item. If one is missing asbestos, slab removal or pool removal, the price gap usually disappears. Cheap quotes with vague inclusions almost always cost more once variations land.

Frequently Asked Questions

How long should a demolition quote be valid?

14–30 days is typical. Tip fees and fuel can move, so we lock in for 30 days from inspection.

Should the quote be fixed-price or estimate?

Always fixed price for residential demolition. If a contractor can't fix the price after a site inspection, walk away.

Do I get a copy of tip dockets?

Yes — we provide tip dockets and any clearance certificates in a single handover pack at job end. Your certifier may require these for occupation certificate purposes.

Related Reading

Direct Demolition is a licensed Sydney demolition contractor (NSW Demolition Licence AD214611). Contact us or call 0451 117 275 for a free site inspection and fixed written quote.

Get a Free Demolition Quote in Sydney

We'll assess your site and give you a fixed-price written quote. No obligation.

0451 117 275Request a Free Quote
Call 0451 117 275